A software company sets up m number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of m is equal to:
- 125
- 160
- 150
- 180
Answer
(3) 150
Solution
Work = 17m computer-days (as planned)
Actually 17 + 8 = 25 days with m, m - 4, m - 8, computers (A.P., d = -4)
252[2m + 24(-4)] = 17m
25(m - 48) = 17m
8m = 1200 m = 150
Answer: (3)